skip to main content
The County of DuPage
Wheaton, Illinois
 

Doing Business with DOT - 75th Street at Book Road

Project Letting Details

Letting DateSectionProject
September 16, 2016
10:00 am
(IDOT Letting)

13-00168-08-SP
Contract No. 61C89

C.H. 33     75th Street
(Book Road intersection)

 Status

  • Advertised.  August 12, 2016.
  • Let on September 16, 2016.
  • Tabulation of bids (totals): Link to IDOT website.
  • Awarded on October 3, 2016.

Advertisement

  • Link to the current IDOT procurement page.
  • Link to the IDOT Transportation Bulletin which includes projects advertised for IDOT (state).
  • Bulletin Date: Friday, August 12, 2016.
  • (Refer to Item 42)
  • Description:  
    Contract No. 61C89 DuPage County District 1
    Section 13-00168-08-SP
    FAP Route 369 (75TH STREET) Project HSIP-43(31)
    Reconstruct the intersection of 75th Street at Book Road. Pavement widening, resurfacing and traffic signal
    modernization; includes 60 unit tree removal; 1,054 cu yd earth excavation; 637 cu yd removal and disposal of unsuitable
    material; 4,038 sq yd topsoil furnish and place; 3,388 sq yd erosion control blanket; 650 sq yd sodding, salt tolerant; 615 ft
    perimeter erosion barrier; 1,592 sq yd aggregate subgrade improvement; 699 sq yd PCC base course; 1,241 lb
    bituminous materials (tack coat); 143 ton HMA binder course; 159 ton polymerized HMA surface course; 4,440 sq yd
    protective coat; 438 sq yd HMA base course; 1,200 sq ft PCC sidewalk; 483 sq yd HMA surface removal; 1,470
    combination curb and gutter removal; 2,360 sq ft sidewalk removal; 1,470 ft combination concrete curb and gutter; 4,317
    ft thermoplastic pavement marking line; 2,308 sq ft pavement marking removal-water blasting; 26 raised reflective
    pavement markers to be removed; 143 ft underground conduit, galvanized steel; 315 ft unit duct, 600V; 2,340 ft electric
    cable in conduit, signal 1; 1,238 ft detector loop; 1,023 ft remove electric cable from conduit; 365 sq yd aggregate path; 40
    recessed reflective pavement markers; 2 steel combination mast arm assemblies and poles; 8 relocate existing signal
    heads; 6 relocate existing pedestrian push buttons; 3 relocate existing traffic signal posts; federally funded.
    (A Special Provision for this contract requires insurance that names additional insureds) (35 Working Days)
    (Job No. C-91-172-14) (0-00101-1001) (See the Special Provisions for the DBE Percentage)

 

Plans, Special Provisions, Proposals, and other forms: