 |
In conjunction with the Tollway project to reconstruct and widen I-88 to provide four lanes in each direction, the Naperville Interchange will be reconfigured to provide more efficient traffic flow through the Naperville Road and Warrenville Road area. The eastbound on-ramps will remain along Naperville Road, but the exit ramps and westbound entrance ramp will be relocated to a new Connector Road to be constructed west of Naperville Road. This will allow traffic to be distributed more evenly between Warrenville Road and Diehl Road and allow improved north-south movement along Naperville Road. Click on the Tollway link below for further information. |
| |
|
|
Start Contruction: August, 2006
Scheduled Completion: Interchange reconfiguration and mainline Tollway work complete in 2008 |
|
|
|
|
| 2008 Pavement Maintenance Contract |
|
|
|
The County's annual resuracing program will include the improvment of several County highways totalling about 10 miles. The work will be done under two separate contracts; South Contract and a North/Central Contract.
The South Contract includes the following roadways:
Plainfield-Naperville Road (87th to 75th)
Cass Avenue (67th to 63rd)
63rd Street (Cass Avenue to Clarendon Hills Road)
Yackley Avenue (Maple to US 34)
Start Construction: June, 2008
Scheduled Completion: September, 2008
The North/Central Contract includes the following roadways:
Army Trail Road (County Farm Road to 84 Court)
Wooddale Road (Belmont to IL 19)
Finley Road (US 34 to IL 56)
Warrenville Road (River Road to South of Ferry Road)
|
|
|
|
Start Construction: July, 2008
Scheduled Completion: October 2008
|
|
|
|
|
| Maple Avenue over the East Branch DuPage River |
|
|
The existing bridge deck will be removed and a new bridge deck constructed. The new bridge deck will be wider to accommodate a separated bike path across the bridge. |
|
|
|
Start Construction: July, 2008
Scheduled Completion: November, 2008 |
|
|
|
|
| Midwest Road (22nd Street to Butterfield Road) |
|
|
Midwest Road will be widened to provide a continuous median/left turn lane to more safely facilitate left turn movements. |
|
|
|
Start Construction: July, 2008
Scheduled Completion: November 2008 |
|
|
|
|
|
|
| Bloomingdale Road (Greenway Drive to Lake Street) |
|
|
Bloomingale Road will be widened at Dunteman Drive and from Fairfield Way to Schick Road to accommodate a left turn lane/center median to more safely facilitate left turn movements. In addition, Bloomingdale Road will be resurfaced from Greenway Drive to Lake Street. |
|
Scheduled Start: Bid opening scheduled for Fall, 2008 to allow time for utilities to relocate prior to the start of construction. Construction would not begin until Spring, 2009.
Scheduled Completion: Fall, 2009 |
|
|
| |
|