Construction - Upcoming
Construction Contract Terminology
Road Alerts
Road Construction Projects
Back to DOT
   
Division of Transportation
Road Construction

DuPage County Roads Currently Under Contract and/or Under Construction

For Additional Information

Call the main office at 630-407-6900 (M-F 8 a.m. to 4:30 p.m.) or click on Project Details link below for more details.


Location Dates Description Impact on Travel More Info

2009 Pavement
Maintenance

(North-central region)

Start Date
7-22-09 est.

Est. Comp. Date
11/15/09

Resurfacing and repair of:
1. Meyers Rd 
2. Villa Ave.
3. Thorndale Ave.
Daily Lane Closures Project Details / Status

2009 Pavement
Maintenance
(South region)

Start Date
7-22-09 est.

Est. Comp. Date
11/30/09

Resurfacing and repair of:
1. Winfield Rd.
2. Warrenville Rd.
3. Maple Ave. / 55th St.
4. Lemont Rd.
5. 31st St.
Daily Lane Closures Project Details / Status

75th Street 
Olympus Drive to
  Oxford Lane

Start Date
1/2009

Est. Comp. Date
06/2011

Widen to three lanes in each direction, bridge reconstruction, pedestrian tunnel. Lane closures on 75th Street and on Washington Street.  Some sidestreet closures.

Project Details 

Construction Status - see Project Details.

Arlington Heights Rd.
At Devon Ave.

Est. Start Date
4/2009

Est. Comp. Date
09/2009

Widen all directions to provide right turn lanes and dual left turn lanes. Daily lane closures.

Project Details 

Construction Status Report

Army Trail Road
At Petersdorf Road

 

Est. Start Date
9/21/09

Est. Comp. Date
11/13/09

Reconstruct approx. 300' of pavement that has settled. Traffic will be reduced to one lane in each direction while each half (stage) is being constructed.

Project Details

Construction Status Report

Belmont Road Grade Separation   (Advanced Contract)

Start Date
11/2008

Est. Comp. Date
9/11/2009

Underground work and construction of the runaround road for the main contract. Daily lane closures will be needed on Belmont.  Complete closures with posted detours will be used on side streets.

Project Details

Construction Status - see Project Details.

Bloomingdale Road
Greeway Drive to Lake Street

Start Date
05/2009

Est. Comp. Date
11/30/09

Widen roadway to five lanes, two lanes in each direction and a left turn lane. Bloomingdale Road will be reduced to a minimum of one lane in each direction in widening areas.

Project Details

Construction Status Report

Illinois Prairie Path
Bridge over the Union Pacific Railroad

Start Date
09/01/09

Est. Comp. Date
10/2010

Partial bridge reconstruction. Bridge closed during construction.  On-road detour posted for Prairie Path users. Project Details/Status

Maple Avenue
Bridge over East Branch DuPage River.

Start Date
7/10/2008

Est. Comp. Date
5/2009

Bridge reconstruction and widening. All lanes open.  Daily lane closures may be needed for final clean-up and punch list.

Project Details 

Construction Status Report

Thorndale Avenue
Bridge over Salt Creek

 

Start Date
4/6/2009

Est. Comp. Date
10/28/2009

Bridge reconstruction and widening. Thorndale Avenue reduced to one lane in each direction.

Project Details

Construction Status Report