| Location |
Dates |
Description |
Impact on Travel |
More Info |
|
2009 Pavement
Maintenance
(North-central region)
|
Start Date
7-22-09 est.
Est. Comp. Date
11/15/09
|
Resurfacing and repair of:
1. Meyers Rd
2. Villa Ave.
3. Thorndale Ave. |
Daily Lane Closures |
Project Details / Status |
|
2009 Pavement
Maintenance
(South region)
|
Start Date
7-22-09 est.
Est. Comp. Date
11/30/09
|
Resurfacing and repair of:
1. Winfield Rd.
2. Warrenville Rd.
3. Maple Ave. / 55th St.
4. Lemont Rd.
5. 31st St. |
Daily Lane Closures |
Project Details / Status |
|
75th Street
Olympus Drive to
Oxford Lane
|
Start Date
1/2009
Est. Comp. Date
06/2011
|
Widen to three lanes in each direction, bridge reconstruction, pedestrian tunnel. |
Lane closures on 75th Street and on Washington Street. Some sidestreet closures. |
Project Details
Construction Status - see Project Details.
|
Arlington Heights Rd.
At Devon Ave. |
Est. Start Date
4/2009
Est. Comp. Date
09/2009
|
Widen all directions to provide right turn lanes and dual left turn lanes. |
Daily lane closures. |
Project Details
Construction Status Report
|
|
Army Trail Road
At Petersdorf Road
|
Est. Start Date
9/21/09
Est. Comp. Date
11/13/09
|
Reconstruct approx. 300' of pavement that has settled. |
Traffic will be reduced to one lane in each direction while each half (stage) is being constructed. |
Project Details
Construction Status Report
|
|
Belmont Road Grade Separation (Advanced Contract)
|
Start Date
11/2008
Est. Comp. Date
9/11/2009
|
Underground work and construction of the runaround road for the main contract. |
Daily lane closures will be needed on Belmont. Complete closures with posted detours will be used on side streets. |
Project Details
Construction Status - see Project Details.
|
|
Bloomingdale Road
Greeway Drive to Lake Street
|
Start Date
05/2009
Est. Comp. Date
11/30/09
|
Widen roadway to five lanes, two lanes in each direction and a left turn lane. |
Bloomingdale Road will be reduced to a minimum of one lane in each direction in widening areas. |
Project Details
Construction Status Report
|
Illinois Prairie Path
Bridge over the Union Pacific Railroad |
Start Date
09/01/09
Est. Comp. Date
10/2010
|
Partial bridge reconstruction. |
Bridge closed during construction. On-road detour posted for Prairie Path users. |
Project Details/Status |
|
Maple Avenue
Bridge over East Branch DuPage River.
|
Start Date
7/10/2008
Est. Comp. Date
5/2009
|
Bridge reconstruction and widening. |
All lanes open. Daily lane closures may be needed for final clean-up and punch list. |
Project Details
Construction Status Report
|
|
Thorndale Avenue
Bridge over Salt Creek
|
Start Date
4/6/2009
Est. Comp. Date
10/28/2009
|
Bridge reconstruction and widening. |
Thorndale Avenue reduced to one lane in each direction. |
Project Details
Construction Status Report
|