DUPAGE PLAN TO END HOMELESSNESS

NEXT            PREVIOUS            HOME

Component #1 - Needs Assessment - Fully functional CMIS  
Objective:  1.5  By 2006, using the CMIS system, complete an annual "gaps analysis" for homeless services.
Responsible Continuum Committee or Task Group: Needs Assessment Committee - CMIS Users Group
Milestones and Action Steps Timeline Resources
2005 2006
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Partners $$
1. Meet with System Administrator, Peg, and Needs Chair to determine fields and reports required. X             Peg White Lijewski  
2. Contract for development of custom report from Bowman System if needed.     X           Bowman systems $$ for development of reports if needed
3. Run report and verify accuracy.         X          
4. Share with Needs Assessment Committee and Chairman's Forum for approval.             X      
                     
                     
                     
TOTAL COST