DuPage County Roads Currently Under Contract and/or Under Construction

For Additional Information

Call the main office at 630-407-6900 (M-F 8 a.m. to 4:30 p.m.) or click on Project Details link below for more details.

LocationDatesDescriptionImpact on TravelMore Info
55th StreetEst. Start Date
March 2019

Est. Comp. Date
November 2019

Intersection widening at Main Street and at Fairview Avenue, and resurfacing between Maple/Dunham and Williams Street.Long-term lane closuresProject Details/Status
GreenbrookBoulevardStart Date
June 2019

Est. Comp. Date
August 2019
Resurfacing Daily lane closures Project Details/ Status
Meyers Road Drainage ImprovementsStart Date
October 2018

Est. Comp. Date
May 2019

Drainage improvements at 18th Street.Daily lane closures Project Details/
Status
St. Charles Road
at President Street
Start Date
September 2018

Comp. Date
December 2018
Traffic signal installation.Daily Lane Closures Project Details/Status
2018 Sidewalk ImprovementsEst. Start Date
Spring 2019

Est. Comp. Date
2019
Sidewalk construction. Daily Lane ClosuresProject Details/ Status