2017 Pavement Maintenance North 

Project Locations

  • CH 5 Glen Ellyn Road (Fullerton Ave. to Army Trail Rd.) Late June thru Mid August
  • CH 9 Bloomingdale Rd. -  (Geneva Rd. to North Ave.) Late May thru mid July.
  • CH 7 St. Charles Rd.- ( Bloomingdale Rd. to Geneva Rd.) Late June thru Late July
  • CH 21 Geneva Rd./ St. Charles Rd. (Western Ave. to Riford Rd.) Early May thru Early August.

 

Updated September 6, 2017

Short Description of Work

DuPage County is  resurfacing multiple roads throughout the County. The project includes pavement surface removal, pavement patching, various curb and sidewalk repairs, placement of a new asphalt surface, and new pavement markings.

Traffic Control

This project will be constructed utilizing daily lane closures.

Contract Cost

 $1,642,863.84

Completion Date

Construction is expected to be  completed by August 25, 2017.

Construction Status

  • All work has been completed.

  • Function/RoleResponsible Party
    Contractor Plote Construction Inc.. 
    Hoffman Estates IL 
     (847) 695-9300
    Design Engineer DuPage County
    Resident Engineer Primera 
    Lisle, IL 
    Project Engineer Dave Tworek (DuPage County) 
    (630) 407-6900