2017 Pavement Maintenance South

Project Locations

  • CH 56 Woodward Avenue - 75th Street to 83rd Street - Late May thru Late June
  • CH 38 63rd Street - I-355 to Williams Street - Early June thru Mid August.
  • CH 1  Raymond Drive - US 34 to ferry Road - Late June thru Late August
  • CH 3   Ferry Road- IL 59 to River Road - Early July thru Late August

 

Updated October 12, 2017

Short Description of Work

DuPage County is  resurfacing multiple roads throughout the County. The project includes pavement surface removal, pavement patching, various curb and sidewalk repairs, placement of a new asphalt surface, and new pavement markings.

Traffic Control

This project will be constructed utilizing daily lane closures.

Contract Cost

 $ 3,815,996.67

Completion Date

Construction was   completed August 28, 2017.

Construction Status

  • Woodward Avenue has been completed.
  • 63rd Street - Work has been completed.
  • Raymond Drive - has been completed.
  • Ferry Rd. - has been completed.
  • Table caption
    Function/RoleResponsible Party
    Contractor K-Five Construction
    Westmont,IL 
     (630) 257-5600
    Design Engineer DuPage County
    Resident Engineer Lochner, Inc.
    Lisle, IL 
    Project Engineer Dave Tworek (DuPage County) 
    (630) 407-6900