2019 Pavement Maintenance - North Region

Updated:Thursday, July 11, 2019

Project Location(s)

  • Bartlett Road - Stearns Rd to Devon Ave
  • Devon Avenue - Bartlett Rd to County Line
  • Stearns Road - IL 59 to Bartlett Rd
  • York Road - IL 19 to Devon Ave (Various Patching Only)

Short Description of Work

This project is a part of DuPage Counties yearly pavement maintenance program to resurface multiple roadways and improve ride quality. Work that will be performed includes: curb and sidewalk repairs; drainage repairs; traffic signal upgrades; pavement resurfacing; and new pavement markings.

Traffic Control

The work will be constructed primarily with daily lane closures. 

Contract Cost

$2,088,656.27

Completion Date

August 30, 2019

Construction Status

York Road:

  • Work at this location is complete.

Devon Avenue

  • Curb, sidewalk, and drainage structure repairs are complete.
  • The final asphalt surface has been placed.
  • Pavement markings are expected to be placed the week of July 15. 

Bartlett Road

  • Curb and drainage structure repairs are complete. 
  • The final asphalt surface is expected to begin being placed on 7/12. 

Stearns Road

  • Curb, sidewalk, and drainage structure repairs are complete.
  • The contractor has begun milling off the existing surface.

 

 

Plans, Special Provisions and Bid Details

Link to plans, special provisions, and bid details.

Function/RoleResponsible Party
Contractor

Arrow Road Construction Company
1445 Oakton Street
Elk Grove Village, IL 60007
(847) 437-0700

Resident Engineer

Chastain & Associates LLC
Schaumburg, IL

Project Engineer

Steve Mlynarczyk, P.E.
DuPage County DOT
(630) 407-6900