2020 Pavement Maintenance - South Region

Updated:Monday, August 3, 2020

Project Location(s)

  • CH 13 Winfield Road - IL 56 (Butterfield Rd) to IL 38 (Roosevelt Rd)
  • CH 32 Mill Street - US 34 (Ogden Ave) to Warrenville Rd
  • CH 25 Meyers Road - 31st Street to IL 56 (Butterfield Rd)
  • CH 9 Main Street-Downers Grove - 63rd St to 55th St
  • CH 15 Cass Avenue - 75th St to 63rd St

Short Description of Work

This project is a part of DuPage Counties yearly pavement maintenance program to resurface multiple roadways and improve ride quality. Work that will be performed includes: curb and sidewalk repairs; drainage repairs;  pavement resurfacing; and new pavement markings.

Traffic Control

The project will be constructed primarily using daily lane closures.

Contract Cost

$4,438,723.23

Completion Date

August 28, 2020

Construction Status

  • Winfield Road::
    • The contractor has completed the removal and replacement of various curb and the repair of drainage structures.
    • Paving of the asphalt surface course and placement of the final pavement markings are complete.
  • Mill Street:
    • The contractor has completed the removal and replacement of various curb, sidewalk, and drainage repairs. 
    • Replacement of a broken pipe between Bella Vista and I-88 began July 1 will be completed July 2nd with all lanes open to traffic by the end of the day.
    • Paving of the asphalt surface course and placement of the final pavement markings are complete.
  • Meyers Road:
    • The contractor has completed the removal and replacement of various curb, sidewalk, and drainage repairs. 
    • The roadway has been milled and the first layer of new asphalt has been placed.
    • Traffic signal detection has been reinstalled and drainage/utility structures have been adjusted back to final grade.
    • Paving of the final asphalt surface course is scheduled to begin August 6th.
  • Main Street - Downers Grove
    • The contractor has completed the removal and replacement of various curb, sidewalk, and drainage repairs. 
    • The roadway has been milled and the first layer of new asphalt has been placed.
    • Traffic signal detection has been reinstalled and drainage/utility structures have been adjusted back to final grade.
    • Paving of the final asphalt surface course is scheduled to begin August 7th.
  • Cass Avenue
    • The contractor has completed the removal and replacement of various curb, sidewalk, and drainage repairs. 
    • The roadway has been milled and the first layer of new asphalt has been placed.
    • The contractor is currently reinstalling traffic signal detection and adjusting drainage/utility structures back to final grade.

Plans, Special Provisions and Bid Details

Link to plans, special provisions, and bid details.

Function/RoleResponsible Party
Contractor

K-Five Construction Corporation
999 Oakmont Plaza Drive, Suite 200
Westmont, IL 60559
(630) 257-5600

Resident Engineer

Primera Engineers, Inc.

Project Engineer

Steve Mlynarczyk, P.E. 
DuPage County DOT
(630) 407-6900