63rd Street at Springside Avenue

Updated:Thursday, July 2, 2020

Project Location(s)

County Highway 38 - 63rd Street
at Springside Avenue 

 

Short Description of Work

A traffic signal will be constructed at the intersection of 63rd Street and Springside Avenue.  The traffic signal will include left turn arrows for 63rd Street, pedestrian signals for each leg of the intersection, and will be wirelessly interconnected to the system including 63rd/Dunham to the east and 63rd/Woodward to the west.

 

Traffic Control

The work will be completed using daily lane closures, as needed.

 

Contract Cost

$301,849.48

Completion Date

50 Working Days are allowed per the contract.

Construction Status

While some preliminary locating of utilities has been performed, traffic signal work is not expected to start for several months due to delays in delivery of mast arms from the manufacturer.

 

Plans, Special Provisions and Bid Details

Link to plans, special provisions, and bid details.

 

 

Function/RoleResponsible Party
Contractor

Thorne Electric, Inc.
P.O. Box 321
Wheaton, IL 60187

Design Engineer

Christopher B. Burke Engineering, Ltd.
Rosemont, IL

Resident Engineer

Knight E/A, Inc. 
Chicago, IL  60601

Project Engineer

Kent Kuper, P.E. (DuPage County)
(630) 407-6900